Lumby man’s death ruled an accident

A Lumby man’s death at a B.C. Hydro substation in eastern B.C. has been classified as accidental.

Provincial coroner Brenda Downey ruled that Brandon William Beday, 33, died of cardiac arrhythmia, the result of electrocution, on Aug. 16, 2010, at a substation near Cranbrook.

In her three-page report, Downey said Beday was terminating current transformer (CT) secondary conductors in a new transformer primary protection and standby protection panel just after 7 p.m. on Aug. 16, 2010. This was being done under the direction of a communication, protection and control technologist.

One of the secondary cables to be terminated in the panels was energized because the cables remained in service as part of the power system to Hydro customers.

Downey’s report says the technologist provided inaccurate information to Beday by stating that all of the secondary cables were de-energized for termination. Beday terminated the conductors of two de-energized cables and while this work was being done, the technologist was called away to assist another electrician in the substation.

Beday sustained an electrocution when he tried to separate the third cable he believed to be de-energized.

An investigation revealed that the secondary cable was not labeled or tagged to indicate its energized status or potential hazard, and there was no B.C. Hydro procedure requiring such labelling or tagging of de-energized cables.

The technologist told the investigators he tagged or labelled “approximately 50 per cent of the time,” but had no explanation as to the reason he chose to do so.

No testing was done for energy prior to Beday separating conductors of a secondary cable, and there is no Hydro procedure for performing this work.

The B.C. Hydro Investigation Compliance Report states three corrective actions are to be implemented as a result of Beday’s death.

Hydro will develop, communicate and implement an interim work procedure for working on or in the proximity of CT secondary circuitry in protection and control panels;

They will develop, field test, finalize, communicate and implement a permanent work procedure for working on or in the proximity of CT secondary circuitry in protection and control panels, and;

A safety task force has been formed to gain understanding as to why such incidents continue to happen, and to develop recommendations for implementation by the company.

 

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

You might like ...

Surrey enforcer killed on the weekend
 
Election 2014: Surrey school trustee candidates unite
 
28th annual Toy Run roars through Fraser Valley
George Canyon plays in Mission
 
New Mission council officially sworn in
 
10 Days of Terror begins in Mission
Teen dating violence focus of Surrey forum
 
Capturing the spirit of wild salmon in Chilliwack
 
Surrey man wanted on weapons trafficking charges now behind bars

Community Events, October 2014

Add an Event

Read the latest eEdition

Browse the print edition page by page, including stories and ads.

Oct 19 edition online now. Browse the archives.