Opponents of the Keystone XL pipeline demonstrate on the Dodge Street pedestrian bridge during rush hour in Omaha, Neb., on Nov. 1, 2017. A federal judge in Montana has blocked construction of the $8-billion Keystone XL pipeline to allow more time to study the project’s potential environmental impact. THE CANADIAN PRESS/AP, Nati Harnik

U.S. judge blocks construction of $10-billion Keystone XL pipeline

Two other export pipelines - expansion of the TransMountain pipeline and Enbridge Inc.’s Line 3 pipeline replacement - also face uncertainty

TransCanada’s $10-billion Keystone XL pipeline project has suffered another setback after a U.S. federal judge blocked its construction to allow more time to study the potential environmental impact.

The Great Falls Tribune reports U.S. District Judge Brian Morris’ order on Thursday came as the Calgary-based energy giant was preparing to build the first stages of the oil pipeline in northern Montana.

Indigenous and environmental groups had sued TransCanada and the U.S. Department of State after Nebraska authorities approved an alternative route to the one TransCanada had proposed through the state.

The groups argued the U.S. State Department violated several acts in issuing a presidential permit for the pipeline without a proper environmental assessment of the changed route.

Morris said in his decision Thursday the government’s analysis didn’t fully study the cumulative effects of greenhouse gas emissions, the effects of current oil prices on the pipeline’s viability or include updated modelling of potential oil spills.

The proposed 1,897-kilometre pipeline would carry crude from Hardisty, Alta., to Steel City, Neb.

READ MORE: Nebraska approves TransCanada’s Keystone XL pipeline

Two other export pipelines, the expansion of the TransMountain pipeline sold to the federal government and Enbridge Inc.’s Line 3 pipeline replacement, also face uncertainty.

The Associated Press

Like us on Facebook and follow us on Twitter.

Just Posted

Monty Python’s Spamalot set for Vernon stage

Big Apple Productions raises silliness to an art form

Vernon RCMP ready to arrest, for kids

Suspects sought for North Okanagan Jail & Bail Thursday, May 30

More classrooms on the way for Vernon students

Minister of Education announces 240-seat expansion at BX Elementary

Grammatically incorrect tagging strikes Vernon bylaw office

Anti-tag team will begin working next week to target such vandalism

Brain Injury Awareness Month brings discussion to Vernon

The Vernon Brain Health Symposium takes place June 1

New airline regulations bring compensation for tarmac delays, over-bookings

Some of the new regulations will roll out in July, while others are expected for December.

Sit-in on Saturday will protest move to curb loitering in Penticton’s downtown

Nanaimo Square Sit-In is taking place from 10 a.m. to 2 p.m.

Friend of accused Kelowna murderer takes the stand

Elrich Dyck’s testimony continued Friday with details from the night Chris Ausman was killed

Crews respond to smoke at Penticton thrift store

The rooftop A/C unit began filling the building with smoke, prompting them to evacuate

Housing provided for women and children fleeing violence in Penticton

Announcement on Friday is part of a provincewide initiative to construct additional housing.

People’s Party of Canada leader talks B.C. trade to Penticton supporters

Maxime Bernier, head of the new federal political party, spoke at Time Winery on Friday

Princeton RCMP recover stolen homework and save the grade

It’s a slightly better excuse than “the dog ate my homework.” Earlier… Continue reading

New Summerland distillery has received recognition

Alchemist Distiller won audience choice award at recent competition

Scheer says it would take Conservatives five years to balance budget

Scheeraccused the Liberal government of spending $79.5 billion of previously unbudgeted funds

Most Read