The Trans Mountain expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C. (Canadian Press file images)

Trans Mountain pipeline expansion cost jumps 70% to $12.6 billion

The estimate of $7.4 billion was made in 2017 by the previous owner

The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.

President and CEO Ian Anderson says the company owned by the federal government has spent $2.5 billion to date, including the impact of delays and additional regulatory processes, leaving an additional $8.4 billion needed to complete the project, plus $1.7 billion of financial carrying costs.

He says the project is now expected to be in service by December 2022.

The estimate of $7.4 billion was made in 2017 by the previous owner, Houston-based Kinder Morgan, Inc., which sold the expansion project and the existing pipeline to the federal government in 2018 for $4.5 billion.

Opponents have attacked the greenhouse gas emission and oil spill risks of the pipeline project but they’ve also charged it will be a money-loser with unproved markets in Asia that will fail financially and leave the public holding the bag.

ALSO READ: Opponents in B.C. to ramp up protests against Trans Mountain pipeline

Anderson says the company is recommending that Ottawa, as owner and lender, set aside a further $600 million reserve for cost impacts beyond the control of Trans Mountain.

Opponents of the pipeline expansion have vowed to do whatever it takes to stop the project despite losing a legal challenge before the Federal Court of Appeal earlier this week.

The four First Nations who lost the court challenge on Tuesday have 60 days to seek leave to appeal to the Supreme Court of Canada.

The expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Trans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

BX Elementary to receive City of Vernon sewer services

Mayor says the school will be required to join the City of Vernon

A Gardener’s Diary: Prepping seedlings in winter

Before planting seedlings, pots must be scrubbed clean

Vernon gallery hosts Art After Dark

Event hosted by the Vernon Public Art Gallery Friday, Feb. 28

Vernon tennis player named Best of BC winner

Sport BC honours Vasek Pospisil for his comeback season after back surgery

Vernon golf course sinks construction on new clubhouse

Owners at The Rise are in a dispute with City of Vernon over tax assessment

51 health professionals send letter to Trudeau, Horgan panning northern B.C. pipeline

They point to studies about the health and climate change risks from pipeline

UPDATE: Firefighter injured in West Kelowna structure fire

West Kelowna fire crews responded to the blaze at 9:53 p.m. Tuesday

Fake meat and a latte? Starbucks adds Beyond Meat in Canada

The Seattle roaster has talked about introducing plant-based patties in the U.S., but has yet to do so

Groundhogs got it wrong: spring isn’t coming soon, Weather Network says

The only part of B.C. to warm up early will be Victoria

Protecting privacy key to stopping spread of COVID-19, B.C. health officials say

The number of coronavirus cases in B.C. remains at seven

Fire crews battle large blaze in West Kelowna

Reports of multiple structures on fire in the Colleen Road area

From seed to salad: Providing purpose for Okanagan inmates

“I planted every one of these, it makes me feel good, they’re like all my little babies.” - inmate Kim

Most Read